Deadline Alert Flow

AdminSphere ships a scheduled flow, Deadline Alert Scheduled, that runs once a day and emails the people on a service task as its due date approaches. It’s installed inactive, so no alerts go out until you activate it.

Each day the flow looks at service tasks whose Status isn’t Completed or Cancelled, that have a Due Date and an Assigned To user. It sends an email when the due date is exactly:

Days before the due date Who gets the email
60 The Assigned To user
30 The Assigned To user and the Reviewer, if there is one
7 The Assigned To user, the Reviewer and the Approver, if they’re set
  • You need the System Administrator profile.
  1. Go to Setup → Process Automation → Flows.

  2. In the list, click Deadline Alert Scheduled. It opens in Flow Builder, in a new browser tab. The toolbar shows the flow as Inactive.

    The Flow Builder toolbar for Deadline Alert Scheduled, showing the Inactive badge and the Activate button at the right

  3. Click Activate. The badge changes to Active, and the button becomes Deactivate.

  4. Close the Flow Builder tab. You don’t need to change anything in the flow.

  • In Setup → Flows, the Active column is checked for Deadline Alert Scheduled.
  • In Setup → Environments → Jobs → Scheduled Jobs, a job named admsphere__Deadline_Alert_Scheduled-1 appears with the type Scheduled Flow and a Next Scheduled Run.
  • You can’t find the flow in the list. The list is sorted by flow label. Scroll down to the D’s.
  • An alert didn’t arrive. Alerts go out only on the 60th, 30th and 7th day before the due date, and only for open tasks with an Assigned To user. Check the task’s Status, Due Date and people fields.